Riverside refit

On track Led by Grace Okafor · Sep 14 to Nov 13

Board
Milestones done
1 of 4
Spent
$14,250
of $38,000
Left in the budget
$23,750
63% of it
Days to go
40
Reopen Nov 13

About

A new counter and bar, a second espresso station and seats for twelve more, without closing the store for more than two days.

Milestones

  1. Plans signed off, doneSep 25
  2. Contractor startsOct 14
  3. Counter and bar fittedOct 30
  4. Reopen with the new layoutNov 13
Tasks
TaskOwnerDueStage
Order the bar stools for Riverside
Ben Lopez
Oct 12To do
Contractor schedule for Riverside
Grace Okafor
Oct 14In progress
Plans signed off for Riverside
Grace Okafor
Sep 25Done

Team

  • Grace OkaforStore manager · Riverside
  • Ben LopezShift lead · Riverside
  • Leo ParkStore manager · Market Street
  • Diego ReyesAccountant · Market Street

Budget

Spent$14,250 of $38,000
Contractor, deposit
$9,500
Plans and permits
$2,350
Second espresso station, deposit
$2,400

Activity

  1. Plans signed offGrace Okafor · Sep 25
  2. Riverside floor plan.pdf addedGrace Okafor · Sep 25
  3. Contractor deposit paid: $9,500Diego Reyes · Sep 28
  4. Contractor starts Oct 14Grace Okafor · Oct 1